SIART and IDSGEORADAR Perform Structural Monitoring at Sant Cugat Pilot

From 27th to 31st July, SIART and IDSGEORADAR were at Sant Cugat pilot for structural monitoring, during the same week drilling works started. The goal was to perform structural monitoring before and during drilling, and see any impact in the school buildings.

IDSGEORADAR installed a Hydra-G system which monitored real-time measurements of sub-millimetric displacements in the administrative building and in the primary school. This system provides the high-accuracy and resolution radar technology. The system was accompanied by an optical and infrared HD camera providing real- time visual inspection of monitored area, draping radar data on a 3D model of the scene created using the radar system.

On the other hand, SIART installed several accelerometers in both buildings, administrative and primary school, to monitor vibrations before and during the first drilling carried out on 31st July. The goal of monitoring before drilling works is to know the building frequency, and see, once the drilling starts, if it has changed due to the vibrations propagation throughout the terrain. Once data has been captured, SIART will analyze them and present some results.

On the left: one of the accelerometers installed by SIART; On the right: Hydra-G system and camera installed by IDSGEORADAR.

Drilling Works Have Started at the Sant Cugat Pilot Site

On 31st July, Catalana De Perforacions (CDP) started the drilling works at the Sant Cugat demo site. The design of the geothermal field consists of 12 boreholes up to 120m deep and one Horizontal Directional Drilling (HDD).

Image 1: location of the 12 boreholes.

While drilling the first well, some problems with the ground material, mainly clays, and the groundwater level at depths beyond around 60 meters were faced. The borehole heat exchangers are double U PERC 100 SDR 11 PN16, with a diameter of 32mm.

On the other hand, on 3rd of August, the works related to the horizontal connection between the collection chamber and the plant room where the Ground Source Heat Pump (GSHP) will be installed, also started.

These works, including the geothermal field and the horizontal connection between the chamber and the plant room, should be completed on 31st August according to schedule.

 

Image 2: the second borehole drilled

 

Image 3: excavation of the collection chamber of the pipes coming from the 12 boreholes