We have finished the geothermal catchment field in Pins del Vallès School in Sant Cugat, one of our five Geofit pilots. It consists of twelve 120 m deep vertical boreholes and one horizontal directional drilling.
Works carried out during the month of August include, on the one hand, drilling, installation of geothermal heat exchangers and pressure tests, and on the other hand, all civil and installation works related to the horizontal connection between wells and the plant room where the ground-source heat pump will be installed.
The next steps to be taken in our Spanish pilot include the installation of the passive cooling in the administrative building designed by Uponor and the installation of the new electrically-driven heat pump provided by Ochsner and currently under tests at AIT Austrian Institute of Technology GmbH laboratory.